PROJECT JUSTIFICATION: CHALLENGES , CONSTRAINTS AND OBSTACLES OVERCOME
The Laguna Altura (PA-18) project presented numerous complex constraints which required a tremendous amount of collaborative work among numerous professional disciplines to achieve design and construction goals while meeting ambitious construction schedules and deadlines. The project challenged the project team to develop and implement engineering design solutions, to offer cooperation and compromise during the extensive permitting process and to provide quality construction methods which resulted in the project’s completion on schedule and on budget.
Time Constraints included a 14-month construction schedule (excluding homes). Approximately 150 construction permits were issued for the work prior to construction.
66 KV UTILITY UNDERGROUNDING
The design and construction of the undergrounding of existing 66kV electrical power lines. This involved coordination with SCE and several agencies. Work was completed prior to grand opening of project.
OPEN SPACE DEDICATION
Approximately 450 acres of Open Space dedicated as part of the City of Irvine Open Space Program including Veeh Creek, natural hillsides to the west expanding the previously dedicated open space in the Laguna Canyon corridor and providing trail linkages.
100 acres Needle grass Mitigation (Restoration) and other environmental mitigation was required for the project.
MAJOR ROADWAY INFRASTRUCTURE
Construction of Lake Forest Drive from Laguna Canyon Road to Bake Parkway
Construction of SR 133 widening along the project frontage
GRADING
Estimated Total Volume of Earthwork was approximately 8,000,000 CY
WATER LINE RELOCATIONS
A large existing recycled water line was relocated due to the project improvements.
ADDITIONAL INFORMATION
The success of the project was a collaborative team effort. The team included several groups within Irvine Community Development Company, public agencies, consultants, and contractors.
|